Government must ‘stop pussyfooting around’ with Euston HS2, union says
A construction worker walks past HS2 signage near to the proposed site of the London Euston HS2

TORY ministers must “stop pussyfooting around” with more delays to the troubled High Speed 2 (HS2) rail project, transport union TSSA is demanding today.

The intervention comes as the National Audit Office (NAO) urges Downing Street to use a new two-year moratorium on fresh construction work at the project’s London terminal in Euston to develop a design that is “affordable, deliverable and value for money.”

In its latest report — out today — the independent body said the government must “reassess expectations for HS2, its budget and the public benefit” amid soaring inflation and the cost-of-living crisis.

The 95th Anniversary Appeal
Support the Morning Star
You have reached the free limit.
Subscribe to continue reading.
Similar stories
Rescue workers form a chain to move debri in desperate efforts to reach the children trapped in the Pantglas Junior School at Aberfan, Glamorgan
Wales / 21 October 2025
21 October 2025
Construction workers during the installation of the first high speed railway platforms for the HS2 project at Old Oak Common station, west London, May 29, 2025
Features / 11 July 2025
11 July 2025
Health Secretary Wes Streeting speaking at the launch of the Government's 10-year health plan during a visit to the Sir Ludwig Guttman Health & Wellbeing Centre in east London, July 3, 2025
Features / 11 July 2025
11 July 2025

US General Stanley McChrystal has been invited to advise on creating a ‘team of teams’ for healthcare transformation. His credentials? He previously ran interrogation bases where Iraqis were stripped naked and beaten, reports SOLOMON HUGHES