Delays totalling 29 years ‘wreaking havoc’ with public services, says Labour
The Caledonian MacBrayne ferry MV Glen Sannox undergoes a sea trial, accompanied by tugs, on a short trip under her own propulsion from Ferguson Marine yard in Port Glasgow, Inverclyde

SCOTTISH ministers were accused today of “wreaking havoc” with public services as Labour cited delays to key infrastructure projects totalling over 29 years.

The party’s criticism followed a progress update on major capital projects across Scotland, highlighting delays caused by construction issues, labour shortages and inflation.

The report identified 19 delayed projects, including the two CalMac ferries being built at Ferguson Marine in Port Glasgow.

The 95th Anniversary Appeal
Support the Morning Star
You have reached the free limit.
Subscribe to continue reading.
Similar stories
Skiers and snowboarders climb up to the remaining snow patches on Meall a'Bhuiridh in Glencoe to take part in the Midsummer Ski. The event, organised by the Glencoe Mountain Resort, is held every year on the weekend closest to the Summer Solstice, June 20, 2021
Aw That / 21 June 2025
21 June 2025

As Scotland’s inept political class hold endless summits on topics ranging from Reform to seagulls, and management culture replaces political leadership, MATT KERR goes for a hike to take his mind off the unfinished, unaddressed and undone

School support workers, who are members of Unison, Unite and GMB Scotland, on the picket line at Portobello High School in Edinburgh, September 26, 2023
Funding / 28 April 2025
28 April 2025

Tackling poverty in Scotland cannot happen without properly funded public services. Unison is leading the debate